Hydro-Québec
Rate M (medium-power, 100 kW–5 MW)
$16.14/kW-mo
- Energy charge
- 0.0577 CAD/kWh
- Peak window
- Winter peak events, December 1 – March 31, 06:00–09:00 & 16:00–20:00
- Interconnection
- Typically 6–12 months (Hydro-Québec technical review)
- Incentives
- Winter peak demand response (GDP) credits; no upfront provincial BESS grant